Project Summary

This project constructed a new 42 million gallon per day water treatment plant for the City of Anacortes.  The new treatment facility treats water from the Skagit River and serves the 56,000 customers in the City of Anacortes, La Conner, nearby Whidbey Island, and two oil refineries on Fidalgo Island. 

The new facility aims to increase capacity, reliability and water quality with a new pretreatment facility, filter facility, pump stations, operations and control center, chemical facility, clear well, and electrical upgrades.

Construction occurred at the site of the existing treatment plant facility and included a new 2.1 million gallon water storage tank.

IMCO Self-Performed Critical Construction Activities:

  • Critical piping tie-ins to the existing plant within very small working windows so as to limit the impact to the existing plant
  • Temporary dewatering system capable of pumping 15 MGD
  • Driving 360 steel pipe piles, approximately 100-feet in length
  • Placing 14,000 cubic yards of structural concrete for tanks and buildings
  • Installing all yard piping including 54-inch ductile iron and 48-inch welded steel pipe systems
  • Erection of all structural and architectural metal systems
  • Install of all mechanical process systems and piping
  • Installation of 5-1,000 horse power high lift turbine pumps
  • Installation of generators to provide temporary power
  • Installation of contractor designed fuel system capable of running generators for seven consecutive days

Details

Location

Mount Vernon, WA

Owner

City of Anacortes

Contract Amount

$56 Million

Engineer

HDR Engineering, Inc.

Construction Manager

MWH Americas

Duration

March 2011 - May 2013