Saddle Mountain Concrete and Panel House Construction

Project Summary

IMCO provided all labor, equipment, and materials necessary to construct cast-in-place concrete foundations and a CMU panel house for Avista’s Saddle Mountain 230 kV Substation. This is the first new substation Avista has allowed a contractor build.  

Details

Location

Othello, WA

Owner

Avista Corporation

Contract Amount

Confidential

Duration

September 2018 - December 2018