Kenyon Street & 24th Avenue Emergency Watermain Repair

Working with the City to restore water service to local community

The City of Seattle hired IMCO to replace a broken 24-inch watermain in West Seattle. IMCO replaced the existing pipe with 700 feet of HDPE pipe via horizontal directional drilling 35-feet underneath Longfellow Creek. The pipe pull took approximately 10 hours and had to be thoughtfully coordinated with area residents and an adjacent elementary school. IMCO connected, pressure-tested, and sanitized the new pipe to restore water service to the area. 

Owner

City of Seattle

Duration

2022- 2023

Construction Services

Design-Bid-BuildOn-Call Support & Immediate Response