Providing seismic stability to Everett’s drinking water supply
IMCO Construction is building a new eight-million-gallon concrete tank. The prestressed and partially buried tank will store the City of Everett’s drinking water. The current tank is susceptible to seismic damage, and this new structure will provide an upgraded system to serve the community. The work includes a new shoring system, dewatering, electrical and instrumentation and control systems, associated piping, and connections into the existing system.
Owner
City of Everett
Contract Amount
$25.5 million
Duration
July 2024 - present
Construction Services
Design-Bid-Build