EVERETT WATER POLLUTION CONTROL FACILITY: VIEW FROM THE TOP
New aerial and site photos of IMCO's GC/CM project show progress at the Everett Water Pollution Control Facility.
New aerial and site photos show IMCO and the City of Everett's Water Pollution Control Facility Project underway. The majority of subcontractor packages are secured and earthwork activity has begun. IMCO's self-performed scope includes driving sheet pile, shoring and structure excavation, and underground pipe and utility installation. The test pile program was completed in June and cranes were mobilized onsite late this spring. This summer and into fall, subcontractors will be onsite driving concrete pile, performing all concrete and structural steel work, and beginning the process equipment/mechanical work for the trickling filter No. 3, Solids Contact Basin, and Secondary Clarifier No. 3. Photos by Sky-Pix, LLC.