Keller Ferry Terminal Improvements
Project Summary
The Keller Ferry Terminal project provided the replacement of pontoons, approach spans, decking, structural framing, railing, anchors, mooring components, coating systems, and the relocation of electrical and mechanical systems from the existing ferry terminals at the Washington State Keller Ferry Terminal.
IMCO had 55 working days to complete the entire project. A small pile driving portion of the project began in April 2019 when Lake Roosevelt water levels are at the lowest. The majority of the work was performed during a 14-day shutdown in July 2019.