King Street Coach Yard Maintenance Facility Improvements Project

Project Summary

The project consisted of modernization of underground utilities, transition from overhead power and communications to underground, and site improvements, which included two new railroad track sections and energy efficient LED site lighting. IMCO worked closely with Amtrak to install 1,700-feet of track.  The new Tracks 406 & 407 were constructed to connect to Lead Track 1.

Details

Location

Seattle, WA

Owner

AMTRAK

Contract Amount

$3.6 Million

Duration

September 2015 - March 2016

Project Highlights

Requirements for Success: • Worked around active Seattle railroad • Intensive coordination & planning with facility personnel • Worked within sensitive construction windows & met the fast-track schedule